48 4. ASSESSMENT › 4.4. Limitation of the derogation in time and conditions aiming to increase competition and integration with the internal market for electricity, Decision_act (EU) 2024/1274

In forcesince 29 Apr 2024

It is understood that by 31 December 2025 the interconnector between Crete and the Greek continental system is expected to be operational, together with the appropriate metering infrastructure enabling Crete to become part of the Greek wholesale electricity markets. Greece confirmed that there will not be any further delay to the completion of the interconnection project.