25 4. ASSESSMENT › 4.1. Small connected systems whose operation poses substantial problems › Substantial problems for the operation of the system, Decision_act (EU) 2024/1274

In forcesince 29 Apr 2024

In the Application, Greece explained the problems it would encounter in operating the electricity system in Crete, were it to apply Regulation (EU) 2019/943 and Directive (EU) 2019/944 in their entirety during the transitional period. The full application of those legal acts would require the integration of Crete in the Greek electricity markets, through a single (‘one-bidding zone scenario’) or two bidding zones (‘two-bidding zones scenario’). The related challenges as submitted in the Application referred to the same substantial problems that had been assessed by the Commission in Decision (EU) 2022/258.