19 3. THE REQUESTED DEROGATION › 3.3. Duration of the requested derogation, Decision_act (EU) 2024/1274

In forcesince 29 Apr 2024

More specifically, Greece submitted that the COVID-19 pandemic brought about considerable delays in the procurement of certain construction materials and services. In addition, the discovery of significant antiquities during the excavation works caused further delays, because the competent archaeological authorities had to be involved in the permitting processes, which were already ongoing. Greece also mentioned that the finding of karstic cavities in the underground area of the construction field meant that works had to be suspended until those cavities were assessed and dealt with sufficiently. Finally, the floods that took place in September 2023 caused further delays to the project as they affected the production process of the steel structure supplier of the converter station in Crete.