On 28 February 2024, the Commission published the Application on its website and invited Member States and stakeholders to provide comments by 27 March 2024. Only one party submitted comments, which related to the installation of additional conventional generation capacity in Crete as well as the remuneration of such capacity. More specifically, the party raised concerns that the applicable remuneration scheme may not be compatible with the EU rules applicable to capacity mechanisms. For the avoidance of doubt, Greece has not requested a derogation from the EU rules applicable to capacity mechanisms, which means that those rules continue to apply to any remuneration schemes for generation capacity in Crete. Hence, the comments received are outside the scope of the present decision. In addition, the present decision is without prejudice to EU State aid law.
4 1. PROCEDURE, Decision_act (EU) 2024/1274
In forcesince 29 Apr 2024