27 4. ASSESSMENT › 4.1. Small connected systems whose operation poses substantial problems › Substantial problems for the operation of the system, Decision_act (EU) 2024/1274

In forcesince 29 Apr 2024

On the one hand, the integration of Crete’s market participants into the Greek electricity market in the one-bidding zone scenario would cause high redispatching costs, which would have to ultimately be paid by the electricity consumers. In any event, metering infrastructure inadequacies would not allow the full participation of Crete market participants in the day-ahead, intraday and balancing electricity markets of Greece. In particular, the necessary metering systems are not in place and will not be before the first quarter of 2024.