On 18 December 2023, Greece submitted to the Commission a new request for derogation (the ‘Application’) from the provisions referred to in recital 1 as regards the island of Crete. In the new request, Greece explained that, due to unforeseeable delays in the relevant construction and licencing processes, the full interconnection of the island of Crete could not take place by the end of December 2023 and requested a new derogation from those provisions until 31 December 2025 or the completion of the full interconnection of the island of Crete with mainland Greece, whichever would come first.
3 1. PROCEDURE, Decision_act (EU) 2024/1274
In forcesince 29 Apr 2024