Greece requested that the derogation be of equal duration as that of the transitional period, namely until the end of 2025, by which time Crete will be fully interconnected to mainland Greece. Greece clarified that while certain network upgrades on the island of Crete will be gradually taking place until the end of 2028, they will not jeopardise the completion and operation of the Phase II interconnection.
17 3. THE REQUESTED DEROGATION › 3.3. Duration of the requested derogation, Decision_act (EU) 2024/1274
In forcesince 29 Apr 2024