40 4. ASSESSMENT › 4.3. No obstruction to the transition towards renewable energy, increased flexibility, energy storage, electro-mobility and demand response, Decision_act (EU) 2024/1274

In forcesince 29 Apr 2024

As indicated in recital 56 of Decision (EU) 2022/258, prior to the completion of the Phase I interconnection, technical limitations were applied to Crete, imposing a maximum penetration of renewables to 25 % of the load, due to operational security constraints. The completion of Phase I relieved, to a certain extent, that limitation imposed on renewables. The hybrid model allows Crete to export its electricity in case of low load and high renewables generation, in order to avoid curtailment of renewables. Greece submitted figures in support of that statement, demonstrating that during 2021 and especially 2022, which marked the first full year of the operation of the Phase I interconnection, there was an increase in RES production compared to previous years.