Recital 12, Decision_act (EU) 2002/132

In forcesince 25 Apr 2001

As the situation had altered since the French authorities' first reply to the Commission in November 1998, they also supplied the following information:

(i)

the first vessel, which should have been delivered originally in July 1997, a deadline which was then postponed by agreement to 31 October 1998, was eventually delivered only in June 1999. Because of the delay, the owner was able to apply the rejection clause. In the absence of another buyer, the price paid was the current market price at the time of delivery, i.e. USD 53 million instead of the contract price of USD 73 million;

(ii)

as regards the other two vessels, the yard decided in January 1999 to halt the construction of the third tanker of which only a few hull sections had been manufactured. The cost of completing the tanker, given productivity in the yard, would have exceeded the possible price paid by the owner; ACHCN accordingly concluded that it was industrially impossible to build the vessel. As regards the second tanker, it was decided to carry on building it to the launch stage and to find a yard outside France which could complete it. At 1 June 1999, the hull was 90 % completed and its launch was planned for October 1999. The decision was based on the need to remove an incomplete hull from a patent slip located right in the centre of the port of Le Havre since it would otherwise have had to be demolished, at a price.