Recital 10, Decision_act (EU) 2002/132

In forcesince 25 Apr 2001

In their comments, the French authorities detailed the events that had resulted in ACHCN not being in control of the industrial process or the financial position. In essence, the shipyard, despite having considerable know-how in the field of shipbuilding, had been unable to meet an overly ambitious challenge, having launched itself into building a type of vessel of which it had no experience. In addition to the lack of experience there had been external problems such as delays in supplies of steel sheet and quality specifications imposed by the shipowner with which the yard had never previously had to deal.