According to the appraisal, the success of SKET SMM depended entirely on whether it won any orders. But even if it did so and approached break-even by 1998, its credit rating would in all probability still have been so low that further guarantees, that is additional aid, would probably have been necessary. The restructuring plan itself forecast a loss of DM 500 000 for 1998. The plans make no earnings forecasts beyond that date.
>TABLE>
Furthermore, it was clear that SKET SMM would have to be restructured by 1998 even without any privatization. Even in the event of a subsequent privatization, aid could therefore not be ruled out in advance.
Under the circumstances, a probably unavoidable slight change of plan or even of schedule would have brought about a situation which would demand further aid. The restructuring plan could not therefore be considered capable of enabling SKET SMM to cover all its costs and generate a minimum return on the capital invested with the result that, upon completion of the restructuring measures, the company would no longer have been dependent on State support and would have been able to compete in the marketplace on its own. The viability criterion set out in the guidelines would therefore not be satisfied.
Proportionality in relation to restructuring costs and benefits
Besides the abovementioned distortive effects on competition due to the granting of aid to a market player in an industry suffering from excess capacity, the amount of aid earmarked and granted under the privatization plan was not related to any expected benefit from the Community's point of view since the expenditure was exceedingly high in relation to the strong likelihood that the restructuring would not be successful under the prevailing circumstances.
>TABLE>
The notified aid represents 95 % of the total restructuring costs and there is no planned private investor involvement. Instead, the restructuring was intended to prepare the ground for a (second) privatization at a later stage, for which more aid would undoubtedly be required.
Implementation of the restructuring plan