, Special Report No 1/95 on the cohesion financial instrument together with the Commission…

In forcesince 12 Jan 1995

2.7. The DGs mentioned above, which in theory must be regarded as leaders in their respective field, play only a passive role within the still very limited framework of inter-departmental cooperation: they analyse the technical aspects connected with the proposals for a decision to grant aid, and in general the relevant departments restrict themselves to checking, on the basis of the background information placed at their disposal, that there are no formal obstacles to the adoption of the decision.

2.8. The replies of the DGs consulted are used by the authorizing officer to prove that the projects are in line with Community policies, in particular those relating to environmental protection, transport and the award of public contracts. Contrary to the usual practice followed in the context of the European Regional Development Fund (ERDF), the DG for Competition is not always consulted despite the implications that some projects may have for competition policy, particularly in the field of air and maritime transport.

2.9. The amount of time that the DGs concerned are allowed during the consultation procedure for examining the documentation relating to the projects (which is, moreover, often incomplete) is in some cases extremely short. In such circumstances, these deadlines do not give the DGs adequate time to acquire detailed knowledge of the quality of the projects, or to enable them to ensure coordination and consistency with other structural measures. The departments need to be allowed enough time to make the checks requested.

2.10. According to Council Directive 85/337 (11), the Member States must take the necessary steps to ensure that public and private projects likely to have considerable impact on the environment are subjected to an assessment of these effects prior to authorization. The Commission sometimes institutes infringement procedures for failure to apply this Directive and such action may be accompanied, for example in the case of the ERDF, by the suspension of payments to the projects concerned which have not been the subject of a preliminary environmental impact study. Nevertheless, under the cohesion financial instrument, the Commission has approved projects for which the environmental impact has not been assessed, for example the Adra bypass project and the Requena-Chiva motorway project (Spain).

  • celex=31985L0337