, Special Report No 1/95 on the cohesion financial instrument together with the Commission…

In forcesince 12 Jan 1995

3.15. The Regulation of the financial instrument specifies that the Community contribution must be the subject of a single commitment, for the total amount of assistance. Where the project financed has to be carried out over a number of years, the amount of the advances that can be paid is calculated in proportion to (which may be up to two thirds) the amount of assistancecorresponding to the expenditure planned for the first year. As a result of this situation, it is financially best for the Member States to submit projects for which most, or even all, of the works have to be carried out during the first year.

3.16. An examination of the Commission's decisions thus shows that the majority of the projects approved were supposed to be finished by the end of 1993 or the beginning of 1994. In Greece, the work for all the projects approved in 1993 was to be completed by the end of March 1994. The Court noted, however, that, given the scale of the works to be carried out, completion by the intended deadlines proved in many cases to be impossible. The approval of numerous requests for extension, submitted by the Member States even after the deadline for the completion of the works, reflects inadequate forecasting and very weak ex ante assessment of the projects.

3.17. Furthermore, the Commission has failed to introduce precise instructions to be followed by the Member States for using the advances and in particular the interest that they may generate. In view of the amounts involved, the large number of projects under way, the projects which are late in being completed and the fact that initially all the payments made are only advances, special monitoring is essential to make sure that these funds, and where applicable the interest earned on them, are actually used for attaining the objectives of the instrument.

4.

THE PROJECTS

The scale of the projects