134 5. ASSESSMENT OF THE REQUESTED DEROGATION › 5.3. Article 64(2c) of the Electricity Regulation › 5.3.2. Article 64(2c) point (b): Primary auction processes – amount of capacity insufficient to address the adequacy concern › 5.3.2.1. Adequacy concern identified by the NRAA › Difference regarding the modelling of capacity resources, Decision_act (EU) 2026/341

In forcesince 11 Aug 2025

The Commission notes that the NRAA assumes a larger share of plants are in maintenance in January, a month where scarcity events occur most frequently. This reduces the availability of resources, thereby affecting the adequacy risk.