41 3. DESCRIPTION OF THE REQUESTED DEROGATION › 3.2. Identification of the adequacy concern › 3.2.1. The reliability standard, Decision_act (EU) 2026/341

In forcesince 11 Aug 2025

In 2024, the Polish Ministry of Climate and Environment reviewed the reliability standard and set it at 3 hours of LOLE [This is defined as the average number of hours per year in which supply is expected to be lower than demand under normal operation of the system.] per year, which corresponds to the value established in Section 2.2.1 of the State aid decision. According to Poland, the standard was based on calculations made in line with the RS methodology adopted by the EU Agency for the Cooperation of Energy Regulators (‘ACER’) and using the parameters calculated by the NRA [The Polish NRA has calculated the VOLL at 80,6 thousand PLN/MWh and the CONE as follows: fixed CONE at 559608 PLN/MWh and variable CONE at 0 PLN/MWh.] and the European resource adequacy assessment (‘ERAA’) for 2023 (‘ERAA 2023’) results. The decision is publicly available [Available online at https://dziennikustaw.gov.pl/DU/2024/1389.].