According to Articles 23(3) and 24(1) of the Electricity Regulation, the European Network of Transmission System Operators for Electricity (‘ENTSO-E’) should develop a methodology based on the principles provided for in Article 23(5) of the Electricity Regulation, to be used for the ERAA and any NRAA [On 2 October 2020, ACER approved the methodology for the ERAA (‘the ERAA methodology’) in accordance with Article 23(3) of the Electricity Regulation. See the ACER Decision on the ERAA methodology at https://www.acer.europa.eu/sites/default/files/documents/Individual%20Decisions_annex/ACER%20Decision%2024-2020%20on%20ERAA%20-%20Annex%20I_1.pdf.]. While the ERAA is based on a central reference scenario of projected demand and supply, which the NRAA must also include, the NRAA may also take additional sensitivities into account (see Articles 23(5) and 24(1) of the Electricity Regulation).
43 3. DESCRIPTION OF THE REQUESTED DEROGATION › 3.2. Identification of the adequacy concern › 3.2.2. Resource adequacy assessments, Decision_act (EU) 2026/341
In forcesince 11 Aug 2025