(27)
Poland proposes introducing supplementary auctions that would also be open to existing plants that exceed the emission limit. Poland explains that the supplementary auctions for a given year will be organised only when the need for additional capacity is justified on the basis of the NRAA results and only if the following conditions are met:
(a)
the main and additional auctions for the given delivery period have been concluded; and
(b)
the main and additional auctions have failed to procure a volume of capacity sufficient to meet the reliability standard for a given delivery period.