7 2. THE EXISTING CAPACITY MECHANISM, Decision_act (EU) 2026/341

In forcesince 11 Aug 2025

According to Article 22(4)(b) of the Electricity Regulation, from 1 July 2025 at the latest, generation capacity that started commercial production before 4 July 2019 (‘existing plants’) and that emits more than 550 g of CO2 of fossil fuel origin per kWh of electricity (‘the emission limit’) and more than 350 kg CO2 of fossil fuel origin on average per year per installed kWe (‘the carbon budget limit’) must not be committed or receive payments or commitments for future payments under a capacity mechanism. This prohibition does not apply to commitments or contracts concluded before 31 December 2019.