72 3. DESCRIPTION OF THE REQUESTED DEROGATION › 3.3. Report accompanying the requested derogation › 3.3.4. Plan to transition away from the participation of capacity emitting more than the emissions limit in capacity mechanisms, Decision_act (EU) 2026/341

In forcesince 11 Aug 2025

As required by Article 64(2d) of the Electricity Regulation, the application is accompanied by a plan with milestones to transition away from the participation of coal in the existing capacity mechanism by the date of the expiry of the requested derogation, including a plan to procure the necessary replacement capacity. In these documents Poland also puts forward measures to address the regulatory and investment barriers identified in recitals (67) to (71).