133 5. ASSESSMENT OF THE REQUESTED DEROGATION › 5.3. Article 64(2c) of the Electricity Regulation › 5.3.2. Article 64(2c) point (b): Primary auction processes – amount of capacity insufficient to address the adequacy concern › 5.3.2.1. Adequacy concern identified by the NRAA › Difference regarding the modelling of capacity resources, Decision_act (EU) 2026/341

In forcesince 11 Aug 2025

The Commission notes that the modelling of the EVA of resources in the NRAA is different from that used in the ERAA. Some of the assumptions that lead to these divergences are not sufficiently substantiated in the NRAA or in the report referred to in Section 3.2.4. In particular, with regard to the EVA, the Commission observes that in the NRAA, economic decisions are simulated on the basis of one isolated calendar year, and future revenues are not considered. By contrast, according to standard economic practice, economic decisions of generators and investors are typically based on the forecasted costs and revenues over a longer period.