Finally on Wieringermeer the Dutch authorities agreed that the construction costs to create the land artificially in the lake were EUR 9892409. However, the Dutch authorities indicated that these costs do not only include the costs of creating the future marina, but also the cost of financing public works, such as wetlands, sewerage, a junction road etc. The total costs of the public works are EUR 4559248. Hence, the net construction costs for the marina were EUR 5333161. The total purchase price was well above these construction costs, hence the Dutch authorities concluded that there is no advantage to the alleged beneficiary. The Dutch authorities did not provide statistical information on the marina at hand, since it has not yet been built.