Recital 13, Decision_act (EU) 2004/114

In forcesince 29 Oct 2003

In practice however, the marina was polluted and suffered from a considerable lack of maintenance. In the purchase agreement between the municipality and the club dated 27 March 2000, the sailing club agreed on taking on board all costs for purification of the water and outstanding maintenance of the harbour facilities. The municipality estimated the costs for outstanding maintenance in 2000 at EUR 272268 and that of purification at EUR 145201. These estimations were carried out by employees of the municipality, based on their practical experience. The municipality deducted these costs from the appraised value of the marina, resulting in a purchase price of EUR 0,45 (one guilder) for the whole marina.