The Commission argued that the construction of the new opening is a matter of compensation of infrastructure by the municipality because of the closure of the previous entrance. This measure does not constitute State aid within the meaning of Article 87(1) of the EC Treaty. Also, the Commission considered the dredging as a compensating measure for the calculated loss of revenue, which was caused by the closure of the previous entrance, carried out by the local authorities. Therefore, neither does this measure constitute State aid within the meaning of Article 87(1) of the EC Treaty.
Recital 19, Decision_act (EU) 2004/114
In forcesince 29 Oct 2003