114 5. ASSESSMENT OF THE REQUESTED DEROGATION › 5.3. Article 64(2c) of the Electricity Regulation › 5.3.1. Article 64(2c) point (a): Primary auction processes (main and additional auctions) › Compliance of primary auctions with Article 22 of the Electricity Regulation, Decision_act (EU) 2026/341

In forcesince 11 Aug 2025

Article 22(1), point (c) of the Electricity Regulation provides that a capacity mechanism must not go beyond what is necessary to address the adequacy concern. The methodology described in recital (14) above ensures that this requirement is met because: (a) the adequacy concern is determined on the basis of consumers’ willingness to pay for capacity (with the amount of capacity to be auctioned being determined by the reliability standard); and (b) the amount of capacity needed to meet the adequacy concern is set taking into account the likely availability of capacity, on the basis of a proposal from the TSO and with the involvement of the NRA.