Investment aid enabling undertakings to improve energy efficiency other than in buildings shall be compatible with the internal market within the meaning of Article 107(3) of the Treaty and shall be exempted from the notification requirement of Article 108(3) of the Treaty, provided that the conditions laid down in this Article and in Chapter I are fulfilled.
Aid shall not be granted under this Article for investments undertaken to comply with Union standards that have been adopted and are in force. Aid may be granted under this Article for investments undertaken to comply with Union standards that have been adopted but are not yet in force, provided that the investment is implemented and finalised at least 18 months before the standard enters into force.
This Article shall not apply to aid for cogeneration and aid for district heating and/or cooling.
Aid for the installation of energy equipment fired by fossil fuels, including natural gas, shall not be exempted under this Article from the notification requirement of Article 108(3) of the Treaty.
The eligible costs shall be the extra investment costs necessary to achieve the higher level of energy efficiency. They shall be determined by comparing the costs of the investment to those of the counterfactual scenario that would occur in the absence of the aid, as follows:
where the counterfactual scenario consists in carrying out a less energy-efficient investment that corresponds to normal commercial practice in the sector or for the activity concerned, the eligible costs shall consist in the difference between the costs of the investment for which State aid is granted and the costs of the less energy-efficient investment;
where the counterfactual scenario consists in carrying out the same investment at a later point in time, the eligible costs shall consist in the difference between the costs of the investment for which State aid is granted and the Net Present Value of the costs of the later investment, discounted to the point in time when the aided investment would be undertaken;
where the counterfactual scenario consists in maintaining the existing installations and equipment in operation, the eligible costs shall consist in the difference between the costs of the investment for which State aid is granted and the Net Present Value of the investment in the maintenance, repair and modernisation of the existing installation and equipment, discounted to the point in time when the aided investment would be undertaken;
In the case of equipment subject to leasing agreements, the eligible costs shall consist in the difference in Net Present Value between the leasing of the equipment for which State aid is granted and the leasing of the less energy-efficient equipment that would be leased in the absence of aid; the leasing costs shall not include costs relating to the operation of the equipment or installation (fuel costs, insurance, maintenance, other consumables), irrespective of whether they are part of the leasing contract.
In all situations listed in the first subparagraph, the counterfactual shall correspond to an investment with comparable output capacity and lifetime that complies with Union standards already in force. The counterfactual shall be credible in the light of legal requirements, market conditions and incentives generated by the EU ETS system.
Where the investment consists in a clearly identifiable investment solely aimed at improving energy efficiency, for which there is no less energy efficient counterfactual investment, the eligible costs shall be the total investment costs.
The costs not directly linked to the achievement of a higher level of energy efficiency shall not be eligible.
For the buildings referred to in paragraph 3, point (b), the investment in improving the energy efficiency of the building may be combined with investments in any or all of the following:
integrated on-site renewable energy installations generating electricity and/or heat;
equipment for the storage of the energy generated by the on-site renewable energy installation;
equipment and related infrastructure incorporated in the building for the recharging of electric vehicles of the building’s users;
investments in the digitalisation of the building, in particular to increase its smart readiness. Eligible investments may include interventions limited to passive in-house wiring or structured cabling for data networks and, if necessary, the ancillary part of the passive network on the private property outside the building. Wiring or cabling for data networks outside the private property is excluded.
In case of any such combined works as set out in the first subparagraph, points (a) to (d), the entire investment cost of the various pieces of equipment shall constitute the eligible costs.
The aid may be granted either to the building owner(s) or to the tenant(s), depending on who is commissioning the energy efficiency works.
The aid intensity shall not exceed 30 % of the eligible costs.
The aid intensity may be increased by 20 percentage points for aid granted to small undertakings and by 10 percentage points for aid granted to medium-sized undertakings.
The aid intensity may be increased by 15 percentage points for investments located in assisted areas fulfilling the conditions of Article 107(3)(a) of the Treaty and by 5 percentage points for investments located in assisted areas fulfilling the conditions of Article 107(3)(c) of the Treaty.
The aid intensity may reach 100 % of the total investment costs where aid is granted in a competitive bidding process, which fulfils all of the following conditions in addition to those laid down in Article 2, point (38):
the aid award shall be based on objective, clear, transparent and non-discriminatory eligibility and selection criteria, defined ex ante and published at least 6 weeks in advance of the deadline for submitting applications, to enable effective competition;
during the implementation of a scheme, in case of a bidding process where all bidders receive aid, the design of said process shall be corrected to restore effective competition in the subsequent bidding processes, for example, by reducing the budget or volume;
ex post adjustments to the bidding process outcome (such as subsequent negotiations on bid results) shall be excluded;
at least 70 % of the total selection criteria used for ranking bids and, ultimately, for allocating the aid in the competitive bidding process shall be defined in terms of aid in relation to the project’s contribution to the environmental objectives of the measure, for example aid requested per unit of energy saved or of energy efficiency gained. Those criteria shall not account for less than 70 % of the weighting of all the selection criteria.
By way of derogation from paragraph 3, points (a) to (d) and paragraph 7, the eligible costs may be determined without the identification of the counterfactual scenario and in the absence of a competitive bidding process. In that case, the eligible costs shall be the total investment costs directly linked to the achievement of a higher level of energy efficiency and the applicable aid intensities and bonuses set out in paragraphs 4, 5 and 6 are reduced by 50 %.