The Dutch authorities for the most part referred back to information submitted before the decision to initiate the procedure, and maintained their position that the planned investment did not contain any State aid component. They reiterated that the investment should be regarded as an investment in public infrastructure, which did not confer a selective advantage on any undertaking and which guaranteed the multifunctional character of the complex. The contractor who would carry out the investment was to be selected through an open tender procedure. The investment, including the expansion of capacity, was needed to maintain the value of the Ahoy complex; of the total EUR 42 million, only EUR 7 million was to be used to increase the capacity of the Ahoy Arena.
33 V. POSITION OF THE DUTCH AUTHORITIES › Comments on the decision to initiate the procedure, Decision_act (EU) 2009/713