Article 64(2c), point (c) of the Electricity Regulation provides that capacity emitting more than the emission limit may be committed or receive payments or commitments for future payments for a period not exceeding one year and for a delivery period which does not exceed the duration of the derogation.
158 5. ASSESSMENT OF THE REQUESTED DEROGATION › 5.3. Article 64(2c) of the Electricity Regulation › 5.3.3. Article 64(2c) point (c): Supplementary auctions › 5.3.3.3. Contract length and duration of the delivery period, Decision_act (EU) 2026/341
In forcesince 11 Aug 2025