Furthermore, the Polish NRA must verify whether the total amount of capacity to be procured under the updated NRAA is justified and, in particular, whether it reflects the needs of the system in situations of simultaneous scarcity.
150 5. ASSESSMENT OF THE REQUESTED DEROGATION › 5.3. Article 64(2c) of the Electricity Regulation › 5.3.2. Article 64(2c) point (b): Primary auction processes – amount of capacity insufficient to address the adequacy concern › 5.3.2.2. Amount of capacity insufficient to address the adequacy concern, Decision_act (EU) 2026/341