In view of the above, the Commission considers that the procedural requirement under Article 64(2c), point (b) of the Electricity Regulation is met, since Poland has confirmed that supplementary auctions will be held only after the primary auctions have been concluded and only if those auctions have failed to procure sufficient capacity to address the adequacy concern identified by the NRAA for the delivery period covered by those auction processes.
148 5. ASSESSMENT OF THE REQUESTED DEROGATION › 5.3. Article 64(2c) of the Electricity Regulation › 5.3.2. Article 64(2c) point (b): Primary auction processes – amount of capacity insufficient to address the adequacy concern › 5.3.2.2. Amount of capacity insufficient to address the adequacy concern, Decision_act (EU) 2026/341
In forcesince 11 Aug 2025