143 5. ASSESSMENT OF THE REQUESTED DEROGATION › 5.3. Article 64(2c) of the Electricity Regulation › 5.3.2. Article 64(2c) point (b): Primary auction processes – amount of capacity insufficient to address the adequacy concern › 5.3.2.1. Adequacy concern identified by the NRAA › Differences regarding assumptions on cross-zonal exchanges, Decision_act (EU) 2026/341

In forcesince 11 Aug 2025

That said, the distribution of estimated hours of energy not served during the year is relevant for dimensioning capacity auctions. Poland could consider this distribution, taking into account situations of simultaneous scarcity, when determining the amounts to be procured through capacity auctions.