The Commission agrees with ACER’s assessment of the assumptions on capacity resources and considers the changes made to the NRAA to be reasonable updates based either on the latest national CONE study or on the latest available information [National-specific cost assumptions were used for the fixed operating costs of existing coal power plants and for assumptions on demand-side response and storage capacity and nuclear, wind and solar power. The latest CONE study was used to estimate the costs of potential new entry technologies.].
130 5. ASSESSMENT OF THE REQUESTED DEROGATION › 5.3. Article 64(2c) of the Electricity Regulation › 5.3.2. Article 64(2c) point (b): Primary auction processes – amount of capacity insufficient to address the adequacy concern › 5.3.2.1. Adequacy concern identified by the NRAA › Differences regarding assumptions on capacity resources, Decision_act (EU) 2026/341
In forcesince 11 Aug 2025