According to Article 24(3) of the Electricity Regulation, where the NRAA identifies an adequacy concern that was not identified in the ERAA, the NRAA must include the reasons for the divergence between the two assessments, including details of the sensitivities used and the underlying assumptions. The NRAA must be published and submitted to ACER for an opinion. ACER’s opinion must assess whether the divergences between the two assessments are justified.
124 5. ASSESSMENT OF THE REQUESTED DEROGATION › 5.3. Article 64(2c) of the Electricity Regulation › 5.3.2. Article 64(2c) point (b): Primary auction processes – amount of capacity insufficient to address the adequacy concern › 5.3.2.1. Adequacy concern identified by the NRAA, Decision_act (EU) 2026/341