105 5. ASSESSMENT OF THE REQUESTED DEROGATION › 5.3. Article 64(2c) of the Electricity Regulation › 5.3.1. Article 64(2c) point (a): Primary auction processes (main and additional auctions) › Maximised participation of capacity providers which meet the emission limits in primary auctions, Decision_act (EU) 2026/341

In forcesince 11 Aug 2025

Finally, capacity units meeting the emission limit will also be eligible to participate in supplementary auctions (see recital (32) above). These auctions will only be conducted if the primary auctions have not succeeded in procuring the amount of capacity necessary to address the adequacy concern (see recital (27)).