To avoid delays in network deployment, the national dispute settlement body should settle disputes in a timely manner and, in any event, within four months of the date of receipt of the request to settle a dispute in the case of disputes on access to existing physical infrastructure and within one month when it concerns transparency on physical infrastructure, coordination of planned civil works and transparency on planned civil works. Exceptional circumstances justifying a delay in the settlement of a dispute could be beyond the control of the dispute settlement bodies, such as insufficient information or documentation that is necessary to take a decision, including the views of other competent authorities that need to be consulted or the high complexity of the file.