Recital 44, Regulation (EU) 2024/1309

In forcesince 29 Apr 2024

To avoid undue delays, competent authorities should determine the completeness of the permit application within 20 working days of the date of receipt. Where the competent authority concludes that the permit application is not complete, it should invite the applicant to provide any missing information within that period. For reasons of equal treatment and transparency, the competent authorities should be able to consider permit applications for civil works to be inadmissible if the minimum information required under this Regulation has not been made available via a single information point no later than two months before the first permit application being submitted to the competent authorities. Where, in addition to permits, rights of way are required for deploying elements of VHCNs, competent authorities should, by way of derogation from Article 43 of Directive (EU) 2018/1972, grant such rights of way within four months of the date of receipt of the application, except in cases of expropriation. Other rights of way not needed in conjunction with permits for civil works should continue to be granted within six months in accordance with Article 43 of Directive (EU) 2018/1972.