57 5. ASSESSMENT OF THE AID › 5.1. EXISTENCE OF STATE AID › 5.1.1. MEASURE 1: REDUCED LEVEL OF THE FINANCIAL GUARANTEES › 5.1.1.1. Selective economic advantage › Applicable legislation, Decision_act (EU) 2018/118

In forcesince 31 Aug 2017cited 1×

According to Article 14(2) of the Directive, the calculation of the guarantee should be made on the basis of (i) the likely environmental impact of the waste facility, and (ii) the assumption that independent and suitably qualified third parties will assess and perform any rehabilitation work needed. The size of the guarantee shall be periodically adjusted in accordance with any rehabilitation work needed.

  • Judgment of the General Court (Second Chamber) of 16 January 2020. Iberpotash, SA v European Commission.Decision

    In its assessment of the existence of State aid, as regards ‘Measure 1’, the Commission states, in particular with respect to the existence of an advantage, in recital 54 of the contested decision, that it is first of all necessary to …

    16 Jan 2020 · 62018TJ0257