2. DETAILED DESCRIPTION OF THE AID › 2.3. Investment project, Decision_act (EU) 2009/697

In forcesince 17 Jun 2009
(16)

The time table below gives an overview of the different steps for both projects Sovello1 and Sovello2.

[See footnote 7.]

Date of event | Sovello1 | Sovello2

Investment decision | 14.1.2005 (date of MJVA1) | End June 2006 (according to German authorities)

Aid application | 27.12.2004 (for GA grant) | 20.2.2006 (for GA grant)

Aid awarding date |

21.4.2005

(GA decision)

15.12.2006

(GA decision; subject to Commission approval)

Land sale contract | 27.6.2005 | 30.6.2006

Start of works | 2005 | July 2006

Notification | 1.9.2005 | 20.12.2006

Planned investment period | 1.1.2005-31.12.2007 | 24.7.2006-30.6.2008

Start of production | February 2006 | Second quarter 2007

Full capacity reached | End June 2006 (30 MWp) | End 2007 (60 MWp)

Commission approval | 7.6.2006 (SME bonus) |