The time table below gives an overview of the different steps for both projects Sovello1 and Sovello2.
[See footnote 7.]
Date of event | Sovello1 | Sovello2
Investment decision | 14.1.2005 (date of MJVA1) | End June 2006 (according to German authorities)
Aid application | 27.12.2004 (for GA grant) | 20.2.2006 (for GA grant)
Aid awarding date |
21.4.2005
(GA decision)
15.12.2006
(GA decision; subject to Commission approval)
Land sale contract | 27.6.2005 | 30.6.2006
Start of works | 2005 | July 2006
Notification | 1.9.2005 | 20.12.2006
Planned investment period | 1.1.2005-31.12.2007 | 24.7.2006-30.6.2008
Start of production | February 2006 | Second quarter 2007
Full capacity reached | End June 2006 (30 MWp) | End 2007 (60 MWp)
Commission approval | 7.6.2006 (SME bonus) |