37 3. GROUNDS FOR INITIATING THE FORMAL INVESTIGATION PROCEDURE, Decision_act (EU) 2009/697

In forcesince 17 Jun 2009

The Commission further observed that the scale of the initial investment (Sovello1, 30 MWp) is not really small scale. On the other hand, compared to the output of Sovello1, the size of Sovello2 (output 60 MWp) does not really seem to be ‘mass production’. The cost multiplication factor is only 2 for Sovello2, whereas it was 13 for the large investment project Qimonda, for which the Commission had come to the conclusion that the notified project did not form a single investment project with a previous pilot project (Commission decision of 30 January 2008 [Commission decision N 872/06, Individual aid to Qimonda (OJ C 170, 5.7.2008, p. 2).], hereafter: the Qimonda decision).