The German authorities argue that the short test period and the early achievement of success and commercialisation should not be considered as negative elements for the qualification of Sovello1 as a pilot project. The German authorities observe that also Marlboro sold its ‘pilot’ production. This is to be explained by the high demand on the market for solar products. In the case of lower yields and cell efficiency, such modules are sold at lower prices. If the yield and cell efficiency targets set forward for Sovello1 had not been reached, the project would have failed, but the output would still have been sold on the market, in order to limit the losses.
57 5. COMMENTS FROM THE GERMAN AUTHORITIES › 5.1. Sovello1 is a pilot project, Decision_act (EU) 2009/697
In forcesince 17 Jun 2009