85 VI. CONCLUSIONS, Decision_act (EU) 2008/283

In forcesince 13 Nov 2007

Second, the Commission must also acknowledge that its press release of 16 July 2003 was such as to give rise for the four coordination centres with an authorisation renewed for an indefinite period on the basis of the order of 26 June 2003 to the legitimate expectation that they could benefit from the incompatible scheme until the date of the Court's judgment as to substance. Since that judgment was delivered on 22 June 2006 and given the fiscal nature of the measure, enjoyment of the legitimate expectation must be extended to allow those coordination centres to benefit from the incompatible scheme until the end of the normal taxable period running on the date of the judgment.