The judgment of the Court states that Decision 2003/757/EC is annulled ‘insofar as it does not lay down transitional measures for those coordination centres with an application for renewal of their authorisation pending on the date on which the contested decision was notified or with an authorisation which expired at the same time as or shortly after the notification of the decision.’ In paragraph 163 of the judgment, the Court spelt out that ‘the expression ‘shortly after’ should be understood as referring to a date so close to that on which the contested decision was notified that the coordination centres concerned did not have the time required to adjust to the change in the regime in question.’
26 V. ASSESSMENT BY THE COMMISSION › 1. Limits to the annulment ordered by the Court, Decision_act (EU) 2008/283
In forcesince 13 Nov 2007