However, the Commission notes that there are serious doubts about the timely implementation of Measure 2. Indeed, during the detailed examination, the Commission was informed by third parties that skeyes was considering to withdraw from the SAS 3 project, which underpins the planned development of the new ATM system. The Belgian authorities did not contest this information, but emphasised that discussions were still ongoing between the involved parties on the future of the project. In light of those observations, the Commission considers that Belgium has not provided adequate assurance on the implementation of the SAS 3 project or on any alternative solutions to be put in place in the event that the project does not materialize.
88 ASSESSMENT OF THE REVISED PERFORMANCE TARGETS DURING THE DETAILED EXAMINATION › Assessment of the measures invoked by Belgium and Luxembourg to justify the observed deviations from the Union-wide cost-efficiency trends › Measure 2, Decision_act (EU) 2023/1336
In forcesince 16 Jun 2023