Greece explain that, by the start of the commercial operation of the interconnector developed in Phase I, the high voltage electricity network of Crete was to be transferred to the Greek Transmission System Operator (‘IPTO S.A.’), which will own and operate those assets from this date. HEDNO S.A. would no longer operate the high voltage network of Crete, but would still operate the low and medium voltage networks. This transfer took place on 1 August 2021, before the start of the commercial operation of the Phase I of the interconnector between Crete and the Greek continental system.
9 2. THE ISLAND OF CRETE › The electricity system, Decision_act (EU) 2022/258
In forcesince 21 Feb 2022