70 5. COMMENTS FROM INTERESTED PARTIES › Regarding the compatibility of the implementation/execution of the Award, Decision_act (EU) 2015/1470

In forcesince 30 Mar 2015

As regards the preliminary compatibility analysis contained in the opening decision, the claimants maintain that it is conceptually flawed since it applies the current Regional Aid Guidelines (‘RAG’) to the implementation/execution of the Award, even though it is plainly obvious that the implementation/execution of the Award is not motivated by any regional development objective. In the claimants’ opinion, and stressing again that the opening decision wrongly assumes that implementing the Award would retroactively reinstate EGO 24, the only aid that could have been granted were the benefits under the EGO 24 scheme. The EGO 24 should then have been assessed under the 1998 RAG, under which they should have been found compatible.