18 2. BACKGROUND › The investment incentives scheme, Decision_act (EU) 2015/1470

In forcesince 30 Mar 2015

The Competition Council challenged the failure to implement its decision before the Bucharest Court of Appeal, which however dismissed the application on 26 January 2001 as inadmissible [Civil Decision No 26; see Award, paragraph 219.]. The inadmissibility was grounded on the fact that EGO 75 was considered a legislative, not an administrative measure, the legality of which the Competition Council could not contest under Law No 143/1999 and that any conflicts between legal provisions had to be resolved by the government and parliament without interference from the courts. The High Court of Cassation of Justice of Romania rejected the Competition Council’s appeal against the Court of Appeal’s decision on 19 February 2002 as inadmissible on similar grounds [See Award, paragraph 224.].