Art. 57h Commission Regulation (EC) No 952/2006 of 29 June 2006 laying down detailed rules for th…

Individual decisions on tenders

In forcesince 1 Oct 2008
1.

Where a maximum amount of the aid has been fixed in accordance with Article 57g(1)(b), the competent authorities of the Member States shall accept tenders notified in accordance with Article 57f which are equal to or lower than the maximum amount without prejudice to Article 57g(2). All other tenders shall be rejected.

2.

Where no maximum amount has been fixed, all tenders shall be rejected.

3.

The competent authorities of the Member States shall adopt decisions referred to in paragraphs 1 and 2 after the publication of Commission’s Decision on aid referred to in Article 57g(1) and notify to tenderers of the outcome of their participation within a deadline of three working days after the publication.

4.

The rights and obligations of the successful tenderer shall not be transferable.