It should first of all be noted that the notified restructuring plan was incomplete: the Dutch authorities did not, for example, submit up-to-date liquidity planning. The restructuring plan did not provide the Commission with the information it needed in order to be able to carry out a full assessment under the guidelines. The Commission had to ask for KH's liquidity costs and for a sensitivity analysis in respect of the various business scenarios. Because of the way KH's business was going, the Dutch authorities did not appear able at any point in time to provide all the required information.
36 6. ASSESSMENT › 6.2. Compatibility of the aid with the common market › 6.2.2. Restoration of viability, Decision_act (EU) 2006/939
In forcesince 19 Jul 2006cited 1×
Judgment of the Court of First Instance (Eighth Chamber) of 1 July 2009. Jan Rudolf Maas and Others v Commission of the European CommunitiesDecision
In paragraph 22 of the contested decision, the Commission states that the restructuring aid in question consists in the conversion of the rescue loan granted by the Kingdom of the Netherlands to KG Holding, plus interest due on the loan, …
1 Jul 2009 · 62007TJ0081