As for ships 6078 and 6079, which were planned to be delivered from the Marghera shipyard, the planned production times of 18 and 19 months were according to the Commission's expert extremely short. In this respect the expert questions the claims made by Italy in its letter dated 25 May 2005 that there would be a learning curve which would reduce the time needed for the later ships in a series. While this assumption is correct when ships are built in the same yard and with the same methods, it is, according to the expert, not correct when the same type of ship is built in different locations, with different teams, as would have been the case under the December 2000 plan.