There were chiefly two reasons for initiating the formal procedure. One was doubts concerning the feasibility of the plan, whereby one of the five ships (ship 6077) was to be built at the Ancona shipyard, involving a complex production process in which hull sections had to be moved for assembly to a second yard (ATSM Trieste) and back to Ancona, since the length of Ancona's dock is shorter than the ship. Furthermore, Ancona had never built a ship of similar complexity before, casting doubts on the ability to manage this operation, not least concerning outfitting. Linked to this, the construction of ship 6077 at Ancona would have implied an exceptionally high amount of outfitting at the Palermo shipyard because of the shift of production from Ancona to Palermo.