The comments from Italy following the initiation of the formal procedure reflect the comments made by Fincantieri, i.e. that the December 2000 plan was challenging but realistic. Italy considers that the delivery dates could have been kept thanks to Fincantieri's production flexibility, in other words its ability to ‘pool’ the construction process by outsourcing to other yards (including some not normally engaged in the building of cruise ships), through an infrastructure and plant investment project dedicated to that end and through advanced building techniques.
22 IV. COMMENTS FROM ITALY, Decision_act (EU) 2006/639